Add MEP Connectors

An important concept to understand before we jump into the next section is MEP connectors. MEP stands for Mechanical, Electrical, and Plumbing in the world of building engineering.

For system engineers, all MEP components require connectors to behave with intelligence. Components created without connectors cannot participate in a system topology. Connectors are primarily logical entities that allow calculating loads within a project. Revit maintains information about loads associated with the spaces in a project. As devices and equipment are placed in spaces, Revit keeps track of the loads based on load type: HVAC, Lighting, Power, Other. The loads associated with the spaces can be viewed in the instance properties for each space and displayed in schedules.

For architects and structural engineers, knowing how to add and remove connectors to loadable families can be useful when using building components, such as manufactured items from Inventor®, or when exporting a building site to civil engineering applications, such as Civil 3D®. For example, you might want to add, move, or delete a connector for a pipe that connects a custom vanity designed in Inventor to a plumbing system in Revit. Or, you might want to modify the connectors on-site utilities, such as gas or water connections, before they are exported with the building site. After the building site is imported into Civil 3D, the connectors on the site utilities become fully functional.

You can learn more about MEP Connectors in Revit documentation. For example here.

Place MEP Connectors

Making it easy for others to connect your design to the building depends on creating
the appropriate MEP connectors. In this lesson you will add MEP Connectors
to the simplified model of the assembly.

Learning Objectives

  • Place MEP connectors using features of the design.
  • Include values for the connectors
  • Add flow, connection, and voltage information.

The completed exercise

  1. Open the Furnace MEP Connectors.iam file.
  2. Enter the BIM Content environment
  3. Start the Duct Connector tool in the MEP Connector panel and select the larger hole on the top of the assembly the Burner Exhaust connector with a Banded Connection Type.
  4. Add a Burner Intake Duct Connector to the other large, round hole on top.
  5. Place a rectangular Furnace Supply Duct Connector to the left end of the furnace. Include the size of the selected face and a flow value of 600.
  6. Create another Duct Connector for the Furnace Return on the right end of the model.
  7. Use the Electrical Connector tool to place a Control Input to the small hole on the right of the bottom of the design.
  8. Add a balanced Power Input Electrical Connection for 20 amp 120 volts.
  9. Next, add a 1” threaded Pipe Connector for Natural Gas input.
  10. Because there’s no specific System type for this, use Other.
  11. Be sure to save your work when complete.