Any referenced datasets can be downloaded from "Module downloads" in the module overview.
Transcript
00:05
The Change Administrator is notified via email if notifications are turned on.
00:11
The change order will also display in the Change Administrator's work list and Vault.
00:16
The Change Administrator can edit the change order if required,
00:20
for example, changing the assignment for the responsible engineer.
00:23
But they cannot edit the ECO number.
00:27
When ready, the Change Administrator promotes the change order to the work state by clicking Submit.
00:33
Submit and Force Approval can also be selected to move the change order directly to the approved state,
00:39
or the change order can be canceled.
00:42
Now at the work state, the responsible engineer is notified and the ECO is added to their work list.
00:49
The responsible engineer reviews comments, attach files, and markups.
00:54
They change the state of the files to work-in-progress,
00:57
then perform the changes required, such as changes to the design, properties, et cetera.
01:03
When finished, they submit the change order for review.
01:07
The approver or approvers are notified.
01:10
The approver reviews the details of the change order, and can reject and reopen,
01:15
reject and cancel, or approve the change order.
01:19
The change order enters the approved state,
01:22
when an approver approves a change order, and the routing does not specify unanimous approval,
01:27
or the routing specifies unanimous approval, and all assigned approvers have approved the change order.
01:34
The Change Administrator is notified and any work-in-progress or In Review/For Review
01:40
items and files on the change order are set to Released.
01:44
The Change Administrator clicks Close Change Order to move the change order to the CLOSED state.
01:51
Notifications are sent regarding closure,
01:54
including to any individuals set up as Notification Users in the routing list.
02:03
In this demonstration, we will process a change order
02:05
starting at the Open state as the Change Administrator role.
02:09
We find the change order in the work list,
02:13
and double click on it in the Change Order List to open it in the change dialog box.
02:20
Select the Comments tab to view the comments,
02:23
and then select the Status tab to show that it's in OPEN state.
02:28
And select the Submit button to assign the work
02:32
to the responsible engineer and move the ECO to the work state.
02:37
Now we'll log out, and then log back in as the responsible engineer.
02:45
The Vault user name is Engineer,
02:50
and we'll double click on the ECO,
02:55
and first select the Comments tab to view the comments.
02:59
And then in the Records tab, we need to change the state of the files so that they can be worked on.
03:06
So we'll select, and then right-click, and select Change State,
03:12
and change the files to be Work-in-Progress state, so that changes can be made.
03:20
Note that the Revision has been bumped to Revision B.
03:23
Now we'll make the change to the files in Inventor.
03:28
Select Open from the right-click menu.
03:31
Yes to check out the files, and we'll make the change to the part Grip.ipt.
03:43
And we'll make a change to the diameter,
03:48
and enter the new diameter value of 0.45 inches,
03:58
and then check out all the files.
04:04
And then go back to the drawing, and you can check in both files.
04:19
Enter a comment, change the diameter, and click OK.
04:26
Now going back into the Vault, into the change order,
04:31
we can now change that state from Work-in-Progress to For Review.
04:42
Now, select the Status tab, and click Submit, to move the change order to the Review state.
04:52
Next since the engineer is also an approver, the change order can be approved.
05:01
Notice though that the Review state is still the current state.
05:06
So now we'll log out, and log back in as the second approver, who is the Approver User.
05:16
And we'll go back into the change order and approve it here.
05:28
Now you can see that it goes to the APPROVED state because of both reviewers having approved it.
05:36
Now we'll log back out, and log in as the Change Administrator role.
05:46
The Change Administrator is now responsible for opening up the change order,
05:52
and releasing those files before closing the change order.
06:02
Once complete, the Change Administrator can now close that change order.
Video transcript
00:05
The Change Administrator is notified via email if notifications are turned on.
00:11
The change order will also display in the Change Administrator's work list and Vault.
00:16
The Change Administrator can edit the change order if required,
00:20
for example, changing the assignment for the responsible engineer.
00:23
But they cannot edit the ECO number.
00:27
When ready, the Change Administrator promotes the change order to the work state by clicking Submit.
00:33
Submit and Force Approval can also be selected to move the change order directly to the approved state,
00:39
or the change order can be canceled.
00:42
Now at the work state, the responsible engineer is notified and the ECO is added to their work list.
00:49
The responsible engineer reviews comments, attach files, and markups.
00:54
They change the state of the files to work-in-progress,
00:57
then perform the changes required, such as changes to the design, properties, et cetera.
01:03
When finished, they submit the change order for review.
01:07
The approver or approvers are notified.
01:10
The approver reviews the details of the change order, and can reject and reopen,
01:15
reject and cancel, or approve the change order.
01:19
The change order enters the approved state,
01:22
when an approver approves a change order, and the routing does not specify unanimous approval,
01:27
or the routing specifies unanimous approval, and all assigned approvers have approved the change order.
01:34
The Change Administrator is notified and any work-in-progress or In Review/For Review
01:40
items and files on the change order are set to Released.
01:44
The Change Administrator clicks Close Change Order to move the change order to the CLOSED state.
01:51
Notifications are sent regarding closure,
01:54
including to any individuals set up as Notification Users in the routing list.
02:03
In this demonstration, we will process a change order
02:05
starting at the Open state as the Change Administrator role.
02:09
We find the change order in the work list,
02:13
and double click on it in the Change Order List to open it in the change dialog box.
02:20
Select the Comments tab to view the comments,
02:23
and then select the Status tab to show that it's in OPEN state.
02:28
And select the Submit button to assign the work
02:32
to the responsible engineer and move the ECO to the work state.
02:37
Now we'll log out, and then log back in as the responsible engineer.
02:45
The Vault user name is Engineer,
02:50
and we'll double click on the ECO,
02:55
and first select the Comments tab to view the comments.
02:59
And then in the Records tab, we need to change the state of the files so that they can be worked on.
03:06
So we'll select, and then right-click, and select Change State,
03:12
and change the files to be Work-in-Progress state, so that changes can be made.
03:20
Note that the Revision has been bumped to Revision B.
03:23
Now we'll make the change to the files in Inventor.
03:28
Select Open from the right-click menu.
03:31
Yes to check out the files, and we'll make the change to the part Grip.ipt.
03:43
And we'll make a change to the diameter,
03:48
and enter the new diameter value of 0.45 inches,
03:58
and then check out all the files.
04:04
And then go back to the drawing, and you can check in both files.
04:19
Enter a comment, change the diameter, and click OK.
04:26
Now going back into the Vault, into the change order,
04:31
we can now change that state from Work-in-Progress to For Review.
04:42
Now, select the Status tab, and click Submit, to move the change order to the Review state.
04:52
Next since the engineer is also an approver, the change order can be approved.
05:01
Notice though that the Review state is still the current state.
05:06
So now we'll log out, and log back in as the second approver, who is the Approver User.
05:16
And we'll go back into the change order and approve it here.
05:28
Now you can see that it goes to the APPROVED state because of both reviewers having approved it.
05:36
Now we'll log back out, and log in as the Change Administrator role.
05:46
The Change Administrator is now responsible for opening up the change order,
05:52
and releasing those files before closing the change order.
06:02
Once complete, the Change Administrator can now close that change order.
How to buy
Privacy | Do not sell or share my personal information | Cookie preferences | Report noncompliance | Terms of use | Legal | © 2025 Autodesk Inc. All rights reserved
Sign in to start learning
Sign in for unlimited free access to all learning content.Save your progress
Take assessments
Receive personalized recommendations
May we collect and use your data?
Learn more about the Third Party Services we use and our Privacy Statement.May we collect and use your data to tailor your experience?
Explore the benefits of a customized experience by managing your privacy settings for this site or visit our Privacy Statement to learn more about your options.